CBC Grade 9 Mathematics Exam Term 1 · Question 26
A construction firm pays casual labourers KSh 500 each per day. 20 labourers, working 8 hours a day, can complete a job in 12 days. If the firm instead uses…
From Test 11 — Compound Proportions and Rates of Work II · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
A construction firm pays casual labourers KSh 500 each per day. 20 labourers, working 8 hours a day, can complete a job in 12 days. If the firm instead uses 15 labourers working 8 hours a day (same daily wage) to complete the same job, what is the TOTAL wage bill, in KSh?
Answer
120000 KSh
Total work = 20 × 8 × 12 = 1,920 labourer-hours. With 15 labourers at 8 hours a day, days needed = 1,920 ÷ (15 × 8) = 16 days. Total wages = 15 labourers × 16 days × 500 = KSh 120,000.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- A group of 10 volunteers, working 5 hours a day, can build a community classroom in 18 days. (a) How many days would…Question 27
- Three tractors, X, Y and Z, would take 12, 15 and 20 hours respectively to plough a large farm alone. (a) How many…Question 28
- A workshop finds that 6 furniture makers, working 8 hours a day, can make 24 wooden chairs in 4 days. The manager…Question 29
- A lead baker and an assistant, working together, can decorate a wedding cake order in 6 hours. The assistant alone…Question 30
- Using the unitary method: 8 tailors can sew 120 school uniforms in 4 days. How many uniforms can 5 tailors sew in the…Question 1
- 12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days…Question 2