CBC Grade 9 Mathematics Exam Term 1 · Question 29
A workshop finds that 6 furniture makers, working 8 hours a day, can make 24 wooden chairs in 4 days. The manager wants to know how many chairs 9 furniture…
From Test 11 — Compound Proportions and Rates of Work II · 3 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
A workshop finds that 6 furniture makers, working 8 hours a day, can make 24 wooden chairs in 4 days. The manager wants to know how many chairs 9 furniture makers, working 6 hours a day, would make in the same 4 days at the same rate. A learner argues: 'Since 9 is more than 6, and 6 is less than 8, the two changes cancel each other out, so the answer is still 24 chairs.' Explain what is wrong with the learner's reasoning, and calculate the correct number of chairs.
Answer
Compound proportion changes don't simply 'cancel out' just because one quantity went up and another went down — the actual sizes of the changes matter, and they must be calculated properly, not eyeballed. The rate per furniture-maker-hour is 24 ÷ (6 × 8 × 4) = 24 ÷ 192 = 0.125 chairs. The new total is 9 × 6 × 4 = 216 furniture-maker-hours, so the correct number of chairs is 216 × 0.125 = 27, not 24.
Rate = 24 ÷ (6×8×4) = 0.125 chairs per furniture-maker-hour. New total = 9×6×4 = 216 furniture-maker-hours. Chairs = 216 × 0.125 = 27.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- A lead baker and an assistant, working together, can decorate a wedding cake order in 6 hours. The assistant alone…Question 30
- Using the unitary method: 8 tailors can sew 120 school uniforms in 4 days. How many uniforms can 5 tailors sew in the…Question 1
- 12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days…Question 2
- A school kitchen uses 45 kg of maize flour to prepare porridge for 150 pupils over 3 days. Using the same daily…Question 3
- 15 farm labourers, working 5 hours a day, can harvest a tea field in 8 days. How many days would 10 labourers, working…Question 4
- A printing press with 6 identical machines running 8 hours a day can print 4,800 textbooks in 5 days. At the same…Question 5