CBC Grade 9 Mathematics Exam Term 1 · Question 30

A lead baker and an assistant, working together, can decorate a wedding cake order in 6 hours. The assistant alone would take 15 hours. A learner argues: 'The…

From Test 11 — Compound Proportions and Rates of Work II · 3 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

A lead baker and an assistant, working together, can decorate a wedding cake order in 6 hours. The assistant alone would take 15 hours. A learner argues: 'The lead baker alone must take 15 − 6 = 9 hours, since that's the difference between the assistant's time and the combined time.' Explain what is wrong with the learner's reasoning, and calculate the correct time the lead baker would take alone, in hours.

Answer

Individual times cannot be found by subtracting one alone-time from a combined time — the relationship must be worked out through RATES. The combined rate is 1/6 of the order per hour, and the assistant's rate is 1/15 per hour, so the lead baker's rate is 1/6 − 1/15 = 5/30 − 2/30 = 3/30 = 1/10 per hour. The lead baker alone would therefore take 10 hours, not 9 — the learner's method happens to land close to the correct answer here, but the reasoning itself is invalid and would fail with different numbers.

Combined rate = 1/6. Assistant's rate = 1/15. Lead baker's rate = 1/6 − 1/15 = 1/10, so alone he takes 10 hours.

Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.