CBC Grade 9 Mathematics Exam Term 1 · Question 2

12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days would 10 workers, working 6 hours a day,…

From Test 11 — Compound Proportions and Rates of Work II · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days would 10 workers, working 6 hours a day, take to complete the same job at the same individual rate?

  1. A100
  2. B60
  3. C75
  4. D16

Answer

D. 16

Total work = 12 × 8 × 10 = 960 worker-hours. New daily rate = 10 workers × 6 hours = 60 worker-hours per day. Days needed = 960 ÷ 60 = 16 days.