CBC Grade 9 Mathematics Exam Term 1 · Question 2
12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days would 10 workers, working 6 hours a day,…
From Test 11 — Compound Proportions and Rates of Work II · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
12 construction workers, working 8 hours a day, can complete a job in 10 days. Using the ratio method, how many days would 10 workers, working 6 hours a day, take to complete the same job at the same individual rate?
- A100
- B60
- C75
- D16
Answer
D. 16
Total work = 12 × 8 × 10 = 960 worker-hours. New daily rate = 10 workers × 6 hours = 60 worker-hours per day. Days needed = 960 ÷ 60 = 16 days.
More Grade 9 Maths questions from this test
- A school kitchen uses 45 kg of maize flour to prepare porridge for 150 pupils over 3 days. Using the same daily…Question 3
- 15 farm labourers, working 5 hours a day, can harvest a tea field in 8 days. How many days would 10 labourers, working…Question 4
- A printing press with 6 identical machines running 8 hours a day can print 4,800 textbooks in 5 days. At the same…Question 5
- Using the unitary method: 4 identical water pumps, each running 6 hours a day, can irrigate a rice paddy in 9 days.…Question 6
- 10 seamstresses, working 7 hours a day, can sew 280 dresses in 4 days. (a) What is the rate of production per…Question 7
- A farm has enough stored feed to last 40 cattle for 21 days. (a) For how many days would the same feed last if the…Question 8