CBC Grade 9 Mathematics Exam Term 1 · Question 7
10 seamstresses, working 7 hours a day, can sew 280 dresses in 4 days. (a) What is the rate of production per seamstress per hour, in dresses? (b) At this…
From Test 11 — Compound Proportions and Rates of Work II · 2 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
10 seamstresses, working 7 hours a day, can sew 280 dresses in 4 days. (a) What is the rate of production per seamstress per hour, in dresses? (b) At this same rate, how many dresses would 14 seamstresses, working 8 hours a day, produce in 5 days?
Answer
(a) 1; (b) 560
(a) Total seamstress-hours = 10 × 7 × 4 = 280. Rate = 280 dresses ÷ 280 hours = 1 dress per seamstress-hour. (b) New seamstress-hours = 14 × 8 × 5 = 560, so dresses = 560 × 1 = 560.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- A farm has enough stored feed to last 40 cattle for 21 days. (a) For how many days would the same feed last if the…Question 8
- 12 workers, working 8 hours a day, complete a job in 15 days. The same job is then assigned to 10 workers, working…Question 9
- A tailoring workshop uses 18 metres of cloth to make 30 shirts. Asked how much cloth is needed for 45 shirts, a…Question 10
- A signwriter can paint a shop's signage alone in 12 hours. Her apprentice can paint the same signage alone in 24…Question 11
- Two photocopier machines, working together, can produce a full set of exam papers in 6 hours. Machine A alone would…Question 12
- Two carpenters, X and Y, are building a fence together. X works exactly twice as fast as Y. Working together, they…Question 13