CBC Grade 9 Mathematics Exam Term 1 · Question 13
Pipe X can fill a pool in 6 hours, and Pipe Y can fill it in 30 hours. Working together, what fraction of the pool do they fill in one hour?
From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
Pipe X can fill a pool in 6 hours, and Pipe Y can fill it in 30 hours. Working together, what fraction of the pool do they fill in one hour?
- A1/36
- B1/5
- C1/15
- D1/180
Answer
B. 1/5
Combined rate = 1/6 + 1/30 = 5/30 + 1/30 = 6/30 = 1/5 of the pool per hour.
More Grade 9 Maths questions from this test
- A tap alone fills a tank in 15 hours, and a second tap alone fills it in 60 hours. What is their combined fill rate…Question 14
- It takes 3 farm workers 2 hours to weed a plot, all working at the same rate. How many worker-hours does the job…Question 15
- Machine A can complete a job in 5 hours, and Machine B can complete the same job in 20 hours. Working together, how…Question 16
- Worker M takes 4 hours to complete a task alone. Working with Worker N, they finish it together in 3 hours. How many…Question 17
- Two pumps working together can drain a tank in 2 hours. Pump A alone would take 3 hours. How many hours would Pump B…Question 18
- Tap C can fill an 800-litre tank in 8 hours, and Tap D can fill the same tank in 8 hours. (a) How many litres do they…Question 19