naQonda

CBC Grade 9 Mathematics Exam Term 1 · Question 17

Worker M takes 4 hours to complete a task alone. Working with Worker N, they finish it together in 3 hours. How many hours would Worker N take to complete the…

From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

Worker M takes 4 hours to complete a task alone. Working with Worker N, they finish it together in 3 hours. How many hours would Worker N take to complete the task alone?

Answer

12

Combined rate = 1/3 per hour. Worker M's rate = 1/4 per hour. Worker N's rate = 1/3 - 1/4 = 4/12 - 3/12 = 1/12 per hour, so N alone takes 12 hours.