CBC Grade 9 Mathematics Exam Term 1 · Question 17
Worker M takes 4 hours to complete a task alone. Working with Worker N, they finish it together in 3 hours. How many hours would Worker N take to complete the…
From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
Worker M takes 4 hours to complete a task alone. Working with Worker N, they finish it together in 3 hours. How many hours would Worker N take to complete the task alone?
Answer
12
Combined rate = 1/3 per hour. Worker M's rate = 1/4 per hour. Worker N's rate = 1/3 - 1/4 = 4/12 - 3/12 = 1/12 per hour, so N alone takes 12 hours.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Two pumps working together can drain a tank in 2 hours. Pump A alone would take 3 hours. How many hours would Pump B…Question 18
- Tap C can fill an 800-litre tank in 8 hours, and Tap D can fill the same tank in 8 hours. (a) How many litres do they…Question 19
- Pipe E can fill a tank in 4 hours, and Pipe F can fill the same tank in 4 hours. A learner says that working together…Question 20
- A matrix has 4 rows and 2 columns. What is its order?Question 21
- Given matrix K = [[5, -2], [3, 8]], what is the element in row 2, column 1?Question 22
- One matrix has order 3x5 and another has order 5x3. Are they compatible for addition?Question 23