Worker P can complete a task in 6 days, and Worker Q can complete the same task in 6 days. Working together, how many days would they take?

From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

Worker P can complete a task in 6 days, and Worker Q can complete the same task in 6 days. Working together, how many days would they take?

  1. A12
  2. B3
  3. C6
  4. D1

Answer

B. 3

Combined rate = 1/6 + 1/6 = 1/3 of the task per day, so together they take 1÷(1/3) = 3 days. (Working together is always FASTER than either alone — adding the individual times, 6+6=12, is a common but wrong shortcut.)