CBC Grade 9 Mathematics Exam Term 1 · Question 21
A road construction company finds that 8 workers, working 10 hours a day, can complete a 2 km road stretch in 15 days. To complete an identical 2 km stretch…
From Test 11 — Compound Proportions and Rates of Work II · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
A road construction company finds that 8 workers, working 10 hours a day, can complete a 2 km road stretch in 15 days. To complete an identical 2 km stretch in only 10 days, while still working 10-hour days, how many workers are needed?
- A10
- B14
- C16
- D12
Answer
D. 12
Total work = 8 × 10 × 15 = 1,200 worker-hours. To finish in 10 days at 10 hours a day, the daily rate needed is 1,200 ÷ 10 = 120 worker-hours per day, so workers needed = 120 ÷ 10 = 12.
More Grade 9 Maths questions from this test
- An electrician takes 5 hours to wire a house alone; his apprentice takes 8 hours alone. They start working together,…Question 22
- A catering team uses 3 cooks working 6 hours to prepare food for a 90-guest school prize-giving lunch. Using the same…Question 23
- 15 farmhands, working 8 hours a day, can harvest a coffee plantation in 6 days. If only 12 farmhands are available and…Question 24
- Two water bowsers deliver water to a school; Bowser A alone would take 6 hours to deliver the full order, Bowser B…Question 25
- A construction firm pays casual labourers KSh 500 each per day. 20 labourers, working 8 hours a day, can complete a…Question 26
- A group of 10 volunteers, working 5 hours a day, can build a community classroom in 18 days. (a) How many days would…Question 27