CBC Grade 9 Mathematics Exam Term 1 · Question 20
Two printing machines, P and Q, working together can print a batch of magazines in 4 hours. Machine P alone would take 6 hours. A learner argues: 'Machine Q…
From Test 11 — Compound Proportions and Rates of Work II · 3 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
Two printing machines, P and Q, working together can print a batch of magazines in 4 hours. Machine P alone would take 6 hours. A learner argues: 'Machine Q alone would take 6 − 4 = 2 hours, since that is the difference between P's time and the combined time.' Explain what is wrong with the learner's reasoning, and calculate the correct time Machine Q would take alone, in hours.
Answer
Times cannot be subtracted directly this way — the relationship between combined time and individual times works through RATES, not times. The combined rate is 1/4 of the job per hour, and P's rate is 1/6 per hour, so Q's rate is 1/4 − 1/6 = 3/12 − 2/12 = 1/12 per hour. Machine Q alone would therefore take 12 hours, not 2 hours — in fact 2 hours cannot be right, since Q must be SLOWER than the combined pair, so Q's own time must be MORE than 4 hours.
Combined rate = 1/4. P's rate = 1/6. Q's rate = 1/4 − 1/6 = 1/12, so Q alone takes 12 hours.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- A road construction company finds that 8 workers, working 10 hours a day, can complete a 2 km road stretch in 15 days.…Question 21
- An electrician takes 5 hours to wire a house alone; his apprentice takes 8 hours alone. They start working together,…Question 22
- A catering team uses 3 cooks working 6 hours to prepare food for a 90-guest school prize-giving lunch. Using the same…Question 23
- 15 farmhands, working 8 hours a day, can harvest a coffee plantation in 6 days. If only 12 farmhands are available and…Question 24
- Two water bowsers deliver water to a school; Bowser A alone would take 6 hours to deliver the full order, Bowser B…Question 25
- A construction firm pays casual labourers KSh 500 each per day. 20 labourers, working 8 hours a day, can complete a…Question 26