12 workers, all working at the same constant rate, can build a wall in 18 days. Part A: Using the unitary method, how many days would 9 workers take to build…
From Test 80 — Final Examination Simulation (Final Mock 2) · 2 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
12 workers, all working at the same constant rate, can build a wall in 18 days. Part A: Using the unitary method, how many days would 9 workers take to build the same wall? Part B: If instead the number of workers is increased to 24, how many days would they take?
Answer
(a) 24; (b) 9
Total work = 12 workers x 18 days = 216 worker-days. Part A: with 9 workers, days = 216/9 = 24 days. Part B: with 24 workers, days = 216/24 = 9 days.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Pipe A can fill a tank alone in 6 hours, and Pipe B can fill the same tank alone in 12 hours. If both pipes are opened…Question 33
- A construction firm finds that 10 machines, working together at the same constant individual rate, can complete a road…Question 34
- A dairy cooperative's 15 identical machines can pack 4,500 milk packets in 6 hours. Working at the same constant rate,…Question 35
- A stock inventory is recorded as matrix K = [[12, 8, 5], [7, 14, 9]]. What is the order of matrix K?Question 36
- Matrix R = [[4, -2, 9], [1, 6, -5], [3, 8, 0]] records the profit, in thousands of shillings, of 3 shops over 3…Question 37
- Matrix X has order 3 x 2 and matrix Y has order 2 x 3. Are X and Y compatible for addition or subtraction, and why?Question 38