CBC Grade 9 Mathematics Mock Exam · Question 34

A construction firm finds that 10 machines, working together at the same constant individual rate, can complete a road section in 18 days. After 6 days of…

From Test 80 — Final Examination Simulation (Final Mock 2) · 3 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

A construction firm finds that 10 machines, working together at the same constant individual rate, can complete a road section in 18 days. After 6 days of work at this rate, 4 machines break down and are removed, and the remaining machines continue at the same individual rate. Explain, showing your working, how many more days the remaining machines will need to complete the road section, and state the total number of days taken from the start of the project.

Answer

Total work = 10 machines x 18 days = 180 machine-days. Work completed in the first 6 days = 10 x 6 = 60 machine-days, leaving 180 - 60 = 120 machine-days of work still to do. With 4 machines removed, 10 - 4 = 6 machines remain, so the additional time needed = 120 / 6 = 20 days. The total time from the start of the project = 6 + 20 = 26 days.

Total work=180 machine-days; done in 6 days=60; remaining=120; with 6 machines, additional days=120/6=20; total=6+20=26 days.

Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.