CBC Grade 9 Mathematics Exam Term 1 · Question 21
15 machines can complete a job in 12 days. How many days would 10 machines take, working at the same rate?
From Test 23 — Term 1 Paper B · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
15 machines can complete a job in 12 days. How many days would 10 machines take, working at the same rate?
Answer
18
15 x 12 = 180 = 10 x days, so days = 180 ÷ 10 = 18.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Worker A alone can finish a task in 14 hours. Worker B alone can finish the same task in 35 hours. Working together,…Question 22
- A prize fund of 68,000 is shared between two winners in the ratio 9:8. (a) What is the value of one share (68,000 ÷…Question 23
- Two pumps are used to drain a flooded field. Pump X alone would take 6 hours, and Pump Y alone would take 10 hours. A…Question 24
- A matrix has 5 rows and 2 columns. What is its order?Question 25
- Matrix M = [[4, -7], [2, 9], [-5, 1]]. What is the element in row 3, column 1?Question 26
- Matrix P has order 3x4 and Matrix Q has order 3x4. Are they compatible for addition? (enter 1 for yes, 0 for no)Question 27