CBC Grade 9 Mathematics Exam Term 1 · Question 24
Two pumps are used to drain a flooded field. Pump X alone would take 6 hours, and Pump Y alone would take 10 hours. A learner argues: 'Using both pumps…
From Test 23 — Term 1 Paper B · 3 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
Two pumps are used to drain a flooded field. Pump X alone would take 6 hours, and Pump Y alone would take 10 hours. A learner argues: 'Using both pumps together will take 6 + 10 = 16 hours, since that's the total time for both.' Explain what is wrong with the learner's reasoning, and calculate the correct time for both pumps working together.
Answer
Adding the individual times gives a LONGER time than either pump alone, which cannot be correct — working together should always take LESS time than either one working alone. The correct approach is to add their rates of work: Pump X drains 1/6 of the field per hour, Pump Y drains 1/10 per hour. Combined rate = 1/6 + 1/10 = 5/30 + 3/30 = 8/30 = 4/15 of the field per hour, so the time taken is 15/4 = 3.75 hours.
Combined rate = 1/6 + 1/10 = 4/15 per hour, so time = 15/4 = 3.75 hours.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- A matrix has 5 rows and 2 columns. What is its order?Question 25
- Matrix M = [[4, -7], [2, 9], [-5, 1]]. What is the element in row 3, column 1?Question 26
- Matrix P has order 3x4 and Matrix Q has order 3x4. Are they compatible for addition? (enter 1 for yes, 0 for no)Question 27
- Given A = [[6, -2], [3, 5]] and B = [[-1, 4], [7, -3]], find the element in row 2, column 2 of A + B.Question 28
- Given C = [[8, -6], [4, 7]] and D = [[-2, 5], [3, -9]]. (a) What is the element in row 1, column 1 of C - D? (b) What…Question 29
- A learner is given two matrices of the same order, A = [[3, 5], [2, 4]] and B = [[1, -2], [6, 0]], and asked to find A…Question 30