If 5 workers can complete a job in 12 days, how many days would 10 workers take, working at the same rate?

From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

If 5 workers can complete a job in 12 days, how many days would 10 workers take, working at the same rate?

  1. A24
  2. B6
  3. C10
  4. D3

Answer

B. 6

Total work = 5×12 = 60 worker-days. With 10 workers: 60÷10 = 6 days. (More workers means FEWER days — this is inverse proportion.)