CBC Grade 9 Mathematics Exam Term 1 · Question 5
6 tailors can sew a batch of uniforms in 20 days. How many tailors would be needed to finish the same batch in 12 days, at the same rate?
From Test 14 — Numbers & Algebra Checkpoint · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
6 tailors can sew a batch of uniforms in 20 days. How many tailors would be needed to finish the same batch in 12 days, at the same rate?
- A10
- B8
- C15
- D4
Answer
A. 10
Total work = 6×20 = 120 tailor-days. In 12 days: 120÷12 = 10 tailors.
More Grade 9 Maths questions from this test
- Share 90 in the ratio 2:7. What is the smaller share?Question 6
- Two amounts are in the ratio 5:7. If the total is 108, what is the larger amount?Question 7
- If 8 machines can produce a batch of items in 15 hours, how many hours would 12 machines take, at the same rate?Question 8
- An amount of 150 is divided in the ratio 2:3:5 among three people. (a) How many parts in total? (b) How much does the…Question 9
- A learner shares 90 in the ratio 4:5 and gives the two shares as 4 and 5 (without scaling up). Explain what is wrong…Question 10
- Tap A can fill a tank in 10 hours, and Tap B can fill the same tank in 40 hours. If both taps are opened together,…Question 11