Recommend THREE corrective safety measures the company should implement immediately. (3 marks)

From End Term 1 2026 — Set 1 · 3 marks · Topic: Foundations of Pre-Technical Studies, Safety in the Work Environment

A construction company is building a two-storey workshop. Workers are using raised platforms without guardrails. Some chemicals such as paint thinners and cleaning agents are stored near open flames. One worker slips and falls, while another suffers skin burns after handling chemicals without gloves.

Recommend THREE corrective safety measures the company should implement immediately. (3 marks)

Answer

Install guardrails; proper labeling and storage; enforce PPE use; remove open flames; provide safety training (any three).