CBC Grade 9 Pre-Technical Studies End Term 1 Exam 2026 · Question 7
For each violation identified, explain the specific risk involved. (4 marks)
From End Term 1 2026 — Set 1 · 4 marks · Topic: Foundations of Pre-Technical Studies, Safety in the Work Environment
A construction company is building a two-storey workshop. Workers are using raised platforms without guardrails. Some chemicals such as paint thinners and cleaning agents are stored near open flames. One worker slips and falls, while another suffers skin burns after handling chemicals without gloves.
For each violation identified, explain the specific risk involved. (4 marks)
Answer
Falling from height → fractures/death; fire hazard → burns/explosion; chemical burns → skin damage; slipping → injuries.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Pre-Technical Studies questions from this test
- Recommend THREE corrective safety measures the company should implement immediately. (3 marks)Question 8
- Evaluate how failure to observe safety regulations can affect Workers. (2 marks)Question 9
- Evaluate how failure to observe safety regulations can affect The company. (2 marks)Question 10
- Explain TWO reasons why the benches cracked. (4 marks)Question 11
- Compare softwood and hardwood in terms of: a) Strength b) Durability c) Cost (6 marks)Question 12
- Propose THREE technical improvements in: a) Material selection b) Joint selection c) Finishing process (5 marks)Question 13