CBC Grade 9 Pre-Technical Studies End Term 1 Exam 2026 · Question 1
A temporary raised platform collapses after being overloaded with cement bags. The main failure was due to lack of:
From End Term 1 2026 — Set 1 · 2 marks · Topic: Foundations of Pre-Technical Studies, Safety in the Work Environment
A temporary raised platform collapses after being overloaded with cement bags.
The main failure was due to lack of:
- AVentilation
- BLoad calculation
- CHeight adjustment
- DPainting
Answer
B. Load calculation
Correct answer: B. Load calculation.
More Grade 9 Pre-Technical Studies questions from this test
- Workers storing chemicals in unlabelled containers increases risk because:Question 2
- A learner draws a cabinet projection but uses full depth instead of half depth. The likely outcome is:Question 3
- A wooden door expands during rainy season and fails to close properly. This problem is mainly caused by:Question 4
- A youth enterprise fails due to poor financial planning. The most probable missing component in their business plan was:Question 5
- Identify FOUR safety violations in the scenario. (4 marks)Question 6
- For each violation identified, explain the specific risk involved. (4 marks)Question 7