naQonda

CBC Grade 9 Mathematics Opener Exam Term 3 2026 · Question 26

6 workers can complete a task in 10 days. If the task needs to be completed in 4 days, determine the number of additional workers required.

From Test 82 — Mathematics Opener Term 3 2026 · 3 marks · Topic: Numbers, Compound Proportions and Rates of Work

6 workers can complete a task in 10 days. If the task needs to be completed in 4 days, determine the number of additional workers required.

Answer

Total work = 6×10 = 60 worker-days. Workers needed = 60÷4 = 15. Additional workers = 15−6 = 9.

Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.

Answer this test freeGet it marked: create a free account

More Grade 9 Maths questions from this test