CBC Grade 9 Mathematics Opener Exam Term 3 2026 · Question 19
Sixty men were employed to complete the construction of a road in 6 days. Forty of them did not turn up. How many more days did it take the remaining men to…
From Test 81 — Mathematics Opener Term 3 2026 · 3 marks · Topic: Numbers, Compound Proportions and Rates of Work
19. Sixty men were employed to complete the construction of a road in 6 days. Forty of them did not turn up. How many more days did it take the remaining men to complete the construction? (3 mks)
Answer
Work = 60 × 6 = 360 man-days. Only 20 men arrive, so they take 360/20 = 18 days, which is 12 more days than planned.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Construct a triangle XYZ in which XY = 6 cm, YZ = 8 cm, and ∠XYZ = 90°. Draw a circle passing through the vertices.…Question 20
- Safaricom foundation donated 225 bags of cement to be shared by school X and Y in the ratio 6:9 respectively.…Question 21
- A classroom measures 15 m long by 8 m wide and 5 m high. All four walls were painted except the doors and the windows.…Question 22
- The circle graph below show how a farmer used his 108 hectares of land. Calculate the number of hectares used for…Question 23
- Draw a triangle with the sides of length 8 cm, 6 cm and 5 cm. Draw a circle which touches the sides of the triangle.…Question 24
- Classify the following numbers as either integer or not integer. (2 mks)Question 1