naQonda

CBC Grade 9 Mathematics Mock Exam · Question 24

A construction task requires 180 worker-hours. (a) How long will 12 workers take? (b) If only 9 workers are available, how much longer will the task take?…

From Test 78 — Full Mock 6 (High-Quality Final Mock) · 5 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

A construction task requires 180 worker-hours. (a) How long will 12 workers take? (b) If only 9 workers are available, how much longer will the task take? Assume equal work rates.

Answer

(a) 180 ÷ 12 = 15 hours. (b) 180 ÷ 9 = 20 hours. The task takes 20 − 15 = 5 hours longer with 9 workers.

12 workers: 15 h. 9 workers: 20 h — 5 hours longer.