CBC Grade 9 Mathematics Mock Exam · Question 24

A team of 15 workers completes a task in 8 days. After 3 days, 5 workers leave. How many more days are needed, assuming the remaining workers continue at the…

From Test 77 — Full Mock 5 (Timed Examination) · 5 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

A team of 15 workers completes a task in 8 days. After 3 days, 5 workers leave. How many more days are needed, assuming the remaining workers continue at the same rate?

Answer

Total work = 15 × 8 = 120 worker-days. Work done in the first 3 days = 15 × 3 = 45 worker-days. Remaining work = 120 − 45 = 75 worker-days. Remaining workers = 15 − 5 = 10, so more days needed = 75 ÷ 10 = 7.5 days.

7.5 more days are needed.