A team of 15 workers completes a task in 8 days. After 3 days, 5 workers leave. How many more days are needed, assuming the remaining workers continue at the…
From Test 77 — Full Mock 5 (Timed Examination) · 5 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
A team of 15 workers completes a task in 8 days. After 3 days, 5 workers leave. How many more days are needed, assuming the remaining workers continue at the same rate?
Answer
Total work = 15 × 8 = 120 worker-days. Work done in the first 3 days = 15 × 3 = 45 worker-days. Remaining work = 120 − 45 = 75 worker-days. Remaining workers = 15 − 5 = 10, so more days needed = 75 ÷ 10 = 7.5 days.
7.5 more days are needed.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Given A=[[1,2],[3,4]] and B=[[2,0],[−1,5]], find A−B and state the order of the result.Question 25
- A line has gradient −2 and passes through (3,4). Find its equation and the x-intercept.Question 26
- Solve 5 − 2x > 11.Question 27
- A circular flower bed has radius 5 m. Find its area and circumference using π=3.142.Question 28
- A rectangular tank measures 2.4 m by 1.5 m by 1.2 m. (a) Find its volume. (b) If filled with water, what mass of water…Question 29
- A lorry carries 7 500 kg of sand in 5 trips. At the same load per trip, how much sand is carried in 8 trips?Question 30