If 4 workers complete a job in 18 days, how many days would 12 workers take at the same rate?
From Test 77 — Full Mock 5 (Timed Examination) · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
If 4 workers complete a job in 18 days, how many days would 12 workers take at the same rate?
- AA. 3
- BB. 54
- CC. 24
- DD. 6
Answer
D. D. 6
Total worker-days = 4 × 18 = 72. With 12 workers: 72 ÷ 12 = 6 days.