CBC Grade 9 Mathematics Mock Exam · Question 4

If 4 workers complete a job in 18 days, how many days would 12 workers take at the same rate?

From Test 77 — Full Mock 5 (Timed Examination) · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

If 4 workers complete a job in 18 days, how many days would 12 workers take at the same rate?

  1. AA. 3
  2. BB. 54
  3. CC. 24
  4. DD. 6

Answer

D. D. 6

Total worker-days = 4 × 18 = 72. With 12 workers: 72 ÷ 12 = 6 days.