CBC Grade 9 Mathematics Mock Exam · Question 24
Eight workers can complete a wall in 12 days. All workers work at the same rate. (a) How many worker-days are required? (b) How many days would 6 workers…
From Test 76 — Full Mock 4 (Full Mock with Visuals) · 5 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
Eight workers can complete a wall in 12 days. All workers work at the same rate. (a) How many worker-days are required? (b) How many days would 6 workers take? (c) Explain why the relationship is inverse.
Answer
(a) 8 × 12 = 96 worker-days. (b) 96 ÷ 6 = 16 days. (c) The total amount of work is fixed; fewer workers means each must do more, so the number of days needed increases as the number of workers decreases — this inverse relationship is why more workers finish faster.
(a) 96 worker-days. (b) 16 days. (c) Workers and days are inversely proportional for a fixed amount of work.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Given A = [[2,1],[3,−2]] and B = [[4,−1],[0,5]], find (a) A + B and (b) 2A. A school uses A to represent two types of…Question 25
- A straight line passes through A(0, −3) and B(4, 5). (a) Find its gradient. (b) Find its y-intercept. (c) Write its…Question 26
- Solve and represent on a number line: −2 ≤ 3x + 1 < 10.Question 27
- A rectangular school garden is 18 m by 12 m. A triangular flower bed with base 6 m and perpendicular height 4 m…Question 28
- A cylindrical water tank has radius 1.4 m and height 2.5 m. Calculate its volume using π = 22/7. Give the answer in…Question 29
- A metal sample has a mass of 5.4 kg and occupies 0.002 m³. (a) Find its density. (b) Another sample has density 2 700…Question 30