Eight workers can complete a wall in 12 days. All workers work at the same rate. (a) How many worker-days are required? (b) How many days would 6 workers…

From Test 76 — Full Mock 4 (Full Mock with Visuals) · 5 marks · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

Eight workers can complete a wall in 12 days. All workers work at the same rate. (a) How many worker-days are required? (b) How many days would 6 workers take? (c) Explain why the relationship is inverse.

Answer

(a) 8 × 12 = 96 worker-days. (b) 96 ÷ 6 = 16 days. (c) The total amount of work is fixed; fewer workers means each must do more, so the number of days needed increases as the number of workers decreases — this inverse relationship is why more workers finish faster.

(a) 96 worker-days. (b) 16 days. (c) Workers and days are inversely proportional for a fixed amount of work.

Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.