Six workers can complete a task in 15 days. At the same rate, how many days would 10 workers take?

From Test 76 — Full Mock 4 (Full Mock with Visuals) · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

Six workers can complete a task in 15 days. At the same rate, how many days would 10 workers take?

  1. AA. 6 days
  2. BB. 9 days
  3. CC. 8 days
  4. DD. 25 days

Answer

B. B. 9 days

Total worker-days = 6 × 15 = 90. With 10 workers: 90 ÷ 10 = 9 days (inverse proportion).