CBC Grade 9 Mathematics Exam Term 1 · Question 28
20 machines can complete an order in 9 days. How many days would 12 machines take, working at the same rate?
From Test 24 — Term 1 End-of-Term Examination · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work
20 machines can complete an order in 9 days. How many days would 12 machines take, working at the same rate?
Answer
15
20 x 9 = 180 = 12 x days, so days = 180 ÷ 12 = 15.
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Maths questions from this test
- Pipe A alone can fill a tank in 20 hours. Pipe B alone can fill the same tank in 30 hours. Working together, how many…Question 29
- Divide 175 into two parts in the ratio 2:5. What is the larger part?Question 30
- A charity fund of 90,000 is shared between two projects in the ratio 4:5. (a) What is the value of one share (90,000 ÷…Question 31
- Pump C alone can empty a pool in 8 hours. Pump D alone can empty the same pool in 24 hours. A learner argues: 'Working…Question 32
- A matrix has order 5x6. How many elements does it contain?Question 33
- A matrix has 9 rows and 2 columns. What is its order?Question 34