20 machines can complete an order in 9 days. How many days would 12 machines take, working at the same rate?

From Test 24 — Term 1 End-of-Term Examination · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

20 machines can complete an order in 9 days. How many days would 12 machines take, working at the same rate?

Answer

15

20 x 9 = 180 = 12 x days, so days = 180 ÷ 12 = 15.