If 4 workers can build a wall in 15 days, how many days would 6 workers take, working at the same rate?

From Test 22 — Term 1 Paper A · 1 mark · Topic: 1.0 Numbers, 1.4 Compound Proportions and Rates of Work

If 4 workers can build a wall in 15 days, how many days would 6 workers take, working at the same rate?

  1. A10
  2. B22.5
  3. C6
  4. D20

Answer

A. 10

More workers means fewer days (inverse proportion): 4 x 15 = 60 = 6 x days, so days = 60 ÷ 6 = 10.