(c) If 8 workers can complete a job in 15 days, how many days would 12 workers take to complete the same job, working at the same rate?

From Mathematics — Term 3 Opener Assessment 2026 (Set 11) · 3 marks · Topic: Numbers, Proportion

27. (c) If 8 workers can complete a job in 15 days, how many days would 12 workers take to complete the same job, working at the same rate?

Answer

10 days

The job takes 8 × 15 = 120 worker-days. Shared among 12 workers: 120 ÷ 12 = 10 days. More workers take fewer days (inverse proportion).

Working

  1. Total work = 8 × 15 = 120 worker-days.
  2. 12 workers: 120 ÷ 12 = 10 days.