CBC Grade 8 Mathematics Revision Exam 2026 · Question 37
In a textile company, 20 employees can knit 1000 sweaters in 7 days. If 6 employees did not turn up for the job, how many more days will the remaining ones…
From Mathematics — Revision 2026 (Booklet 6) · 3 marks · Topic: Numbers, Proportion
32. In a textile company, 20 employees can knit 1000 sweaters in 7 days. If 6 employees did not turn up for the job, how many more days will the remaining ones take to knit the same number of sweaters? (3mks)
Answer
3 more days
Fewer workers, more days.
Working
- 20 × 7 = 140 worker-days
- 140 ÷ 14 = 10 days
- 10 − 7 = 3 more days
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 8 Maths questions from this test
- The sales in a shop in a week reduced from sh. 35 000 to sh. 28 000. What was the ratio decrease? (2mks)Question 41
- a) Round off the amount of petrol correct to 2 decimal places. (1mk)Question 42
- b) How many significant figures does the amount of petrol has? (1mk)Question 43
- Lany drove at an average speed of (x − 3) km/h and covered a distance of (2x − 6) km. Find the time he took to cover…Question 44
- A circular pond of diameter 21 cm is fenced using five strands of barbed wire. Calculate the length of the wire used…Question 45
- Find the area of a sector of a circle that subtends an angle of 90° given the radius of the circle is 28 cm. (π =…Question 46