CBC Grade 8 Mathematics Revision Exam 2026 · Question 37

In a textile company, 20 employees can knit 1000 sweaters in 7 days. If 6 employees did not turn up for the job, how many more days will the remaining ones…

From Mathematics — Revision 2026 (Booklet 6) · 3 marks · Topic: Numbers, Proportion

32. In a textile company, 20 employees can knit 1000 sweaters in 7 days. If 6 employees did not turn up for the job, how many more days will the remaining ones take to knit the same number of sweaters? (3mks)

Answer

3 more days

Fewer workers, more days.

Working

  1. 20 × 7 = 140 worker-days
  2. 140 ÷ 14 = 10 days
  3. 10 − 7 = 3 more days