If 10 men can complete a task in 6 days, how many men are needed to complete the same task in 2 days? (2 marks)

From Mathematics Formative Assessment · 2 marks · Topic: Mathematics, Numeracy and Problem Solving

Give non-exact numerical answers to 3 significant figures unless a different accuracy is stated. Show your working. Use π = 3.142 unless otherwise stated.

If 10 men can complete a task in 6 days, how many men are needed to complete the same task in 2 days? (2 marks)

Answer

Assuming equal constant work rates: Work = 10 × 6 = 60 worker-days. Workers needed = 60 ÷ 2 = 30.