The map below shows hydroelectric power projects in Africa. Use it to answer the question that follows. Name the power projects marked A and E. (2mks)
From Test 14 — Social Studies Midterm Examination (KJSEA Prediction Series, Term 3 2025) · 2 marks · Topic: Resources and Economic Activities, Natural Resources and Their Use
The map below shows hydroelectric power projects in Africa. Use it to answer the question that follows.

The map below shows hydroelectric power projects in Africa. Use it to answer the question that follows. Name the power projects marked A and E. (2mks)
Answer
A: Aswan High Dam (Egypt). E: Seven Forks Scheme (Kenya).
Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.
More Grade 9 Social Studies questions from this test
- (f) State three benefits of hydroelectric power projects. (3mks)Question 46
- (g) Give two reasons why urbanization is growing rapidly in Africa. (2mks)Question 47
- (h) Match each instrument with what it measures: thermometer, rain gauge, wind vane, barometer — against: amount of…Question 48
- (i) Give two factors that influence climate. (2mks)Question 49
- (j) Mention two human activities that lead to water pollution. (2mks)Question 50
- The diagram below shows some weather station instruments. Identify the instruments marked K, L, and M. (3 marks)Question 51