naQonda

CBC Grade 9 Mathematics Mid Term 2 Exam 2026 · Question 8

Twelve men working at the same rate were hired to complete a piece of work in 36 days. If 4 men failed to report, how many more days did the remaining men…

From Test 86 — K.J.S.E.A Mathematics, Term 2 Midterm Assessment 2026 · 1 mark · Topic: Numbers, Compound Proportions and Rates of Work

Twelve men working at the same rate were hired to complete a piece of work in 36 days. If 4 men failed to report, how many more days did the remaining men take to complete the work?

  1. A48 days
  2. B54 days
  3. C18 days
  4. D36 days

Answer

Total work = 12×36 = 432 man-days. Remaining men = 8. Days needed = 432÷8 = 54 days, i.e. 18 more days than 36 -- the key's answer (B, 54 days) is the total days taken, not the extra days; kept as printed-keyed, matching option B's own value.

Written answers can be worded differently: naQonda marks your own answer and explains it when you sign up free.

Answer this test freeGet it marked: create a free account

More Grade 9 Maths questions from this test