- Question 1: Using the isometric view of a rectangular fruit crate with three equal compartments shown below, draw the following orthographic views in…Answer: A correct answer lays out three views in first-angle projection: End Elevation to the left of the Front…
- Question 2: Using the standard rule that a tenon's thickness should be about one-third of the timber's thickness: (i) calculate the tenon's thickness;…Answer: Tenon thickness ≈ 20mm ÷ 3 ≈ 6-7mm (commonly set to 6mm to match a standard marking gauge/chisel size).…
- Question 3: Describe, in the correct order, the steps and technique needed to cut this mortise and tenon joint accurately. In your answer, explain…Answer: Correct sequence: (1) mark out the shoulder and cheek lines on both timber pieces using the marking gauge,…
- Question 4: After assembly, a learner's finished joint shows the tenon fitting into the mortise but with a visible 1-2mm gap along one side, and the…Answer: The visible gap along one side means the tenon was cut slightly undersized (or the mortise cut slightly…
- Question 5: State ONE thing a woodworker should do to achieve a neat, well-finished joint once it is assembled. (1 mark)Answer: Lightly sand or plane any rough edges flush, and remove visible pencil/gauge marking lines so the finished…
- Question 6: Draw a circuit diagram to wire the solar panel and rechargeable battery to a single SPST switch, an LED, and a buzzer, so that the LED and…Answer: A correct diagram shows the solar panel and rechargeable battery supplying the circuit, a single SPST switch…
- Question 7: Explain why the LED and buzzer must be connected in PARALLEL rather than in SERIES for this application. What would happen to the…Answer: In parallel, the LED and buzzer are each connected directly across the full supply voltage, so both operate…
- Question 8: State ONE practice that would help keep this circuit's wiring neat and organised, and ONE safety precaution to observe when stripping and…Answer: Neatness: trim wires to a sensible length and route them tidily along the baseboard rather than leaving them…